Dependency Chain
Battery procurement (₹85L) → Industry Field Trial
Procurement → Milestone · slack 6 days
Source FactBlockingOpen milestone →CleanTech pilot site readiness → Industry Field Trial
Partner → Milestone · slack 6 days
Source FactBlockingOpen milestone →Industry Field Trial → Final Validation
Milestone → Milestone · slack 28 days
Source FactDownstreamOpen milestone →Validation Report → IP Filing
Deliverable → Milestone · slack 0 days
Source FactBlockingOpen milestone →Utility telemetry feed → Grid Simulation Release 3
Partner → Milestone · slack 35 days