Milestones

Milestone Intelligence

Committed plan versus current execution state, continuously derived from approved sources.

6 milestones
MilestoneProjectCommitted DateLatest ExpectedVarianceHealthEvidenceOwner
Prototype v2.0Advanced Materials15 Sep 202615 Sep 20260 daysOn TrackValidatedDr. Meera Rao
Industry Field TrialClean Energy30 Sep 202608 Oct 2026+8 daysAt RiskPartialProf. Anil Kumar
Annual Report — Year 2All Projects15 Oct 202615 Oct 20260 daysOn Track68% CompletePMO
IP FilingBioengineering31 Oct 202618 Nov 2026+18 daysDelayedMissingDr. Karan Shah
Final ValidationClean Energy20 Dec 202620 Dec 20260 daysPlannedMissingProf. Anil Kumar
Grid Simulation Release 3Grid Integration05 Nov 202605 Nov 20260 daysOn TrackValidatedProf. S. Venkatesh
AI InferenceVariance interpretation
Two milestones carry forecast variance. Both trace to blocking dependencies rather than research progress: procurement on Clean Energy and a missing validation report on Bioengineering.