Read-only extract from the institutional ERP, linked to the milestones each item supports.

Procurement Register

ItemValue (₹ L)StatusLinked milestoneMilestone dueSchedule impact
Battery modules — field trial85PO pendingIndustry Field Trial30 Sep 2026+8 days
Environmental chamber46PO releasedPrototype v2.015 Sep 2026None
Electrolyte precursors12DeliveredPrototype v2.001 Sep 2026None
Bio-reactor consumables9Requisition raisedIP Filing31 Oct 2026Low
AI InferenceProcurement → milestone risk
One pending purchase order (battery modules, ₹85 L) is the single largest schedule driver in the Centre, adding an estimated 8 days to the Industry Field Trial.