Overview

Programme Overview

A continuously updated view of progress, risks, resources and review readiness.

Project Portfolio Status

On Track11
At Risk4
Delayed3

18 projects across 5 themes

Review readiness breakdown

Milestones & Deliverables88%
Research Outcomes85%
Partner Commitments80%
Financial Documentation90%

Funding Utilisation

Sanctioned

120 Cr

Utilised

78 Cr

Remaining

42 Cr

65% utilised at the Year 2 review point (plan: 68%).

Data sourced from approved finance / procurement systems. Morelo does not replace the ERP.

Open funding view

Key Upcoming Milestones

Milestone intelligence →
MilestoneProjectOwnerDue DateStatusEvidenceDependency
Prototype v2.0Advanced MaterialsDr. Meera Rao15 Sep 2026On Track4 Evidence Items
Industry Field TrialClean EnergyProf. Anil Kumar30 Sep 2026At Risk2 Evidence ItemsProcurement
Annual Report — Year 2All ProjectsPMO15 Oct 2026On Track68% CompleteMultiple
IP FilingBioengineeringDr. Karan Shah31 Oct 2026Delayed1 Evidence ItemValidation Report

What Needs Attention

AI Inference

Industry Field Trial

Critical

Procurement dependency unresolved

Due in 24 days · Owner: Prof. Anil Kumar

Partner Commitment Overdue

Critical

CleanTech Industries — data-sharing commitment delayed by 18 days

Partner engagement at risk · Owner: Partnership Lead

Deliverable Evidence Missing

At Risk

Prototype Validation Report marked complete — no validated evidence attached

Governance exposure · Owner: Dr. Meera Rao

Research Outcome Imbalance

At Risk

Strong publication progress, translation outcomes below plan

90 days without translation movement · Owner: Centre Director

AI InferenceProgramme-level interpretation
Execution is broadly on plan, but a single dependency chain — pending battery procurement and deferred partner-site readiness — currently accounts for two of the four critical risks and the largest single drag on review readiness.