Milestone Intelligence
Committed plan versus current execution state, continuously derived from approved sources.
6 milestones
| Milestone | Project | Committed Date | Latest Expected | Variance | Health | Evidence | Owner |
|---|---|---|---|---|---|---|---|
| Prototype v2.0 | Advanced Materials | 15 Sep 2026 | 15 Sep 2026 | 0 days | On Track | Validated | Dr. Meera Rao |
| Industry Field Trial | Clean Energy | 30 Sep 2026 | 08 Oct 2026 | +8 days | At Risk | Partial | Prof. Anil Kumar |
| Annual Report — Year 2 | All Projects | 15 Oct 2026 | 15 Oct 2026 | 0 days | On Track | 68% Complete | PMO |
| IP Filing | Bioengineering | 31 Oct 2026 | 18 Nov 2026 | +18 days | Delayed | Missing | Dr. Karan Shah |
| Final Validation | Clean Energy | 20 Dec 2026 | 20 Dec 2026 | 0 days | Planned | Missing | Prof. Anil Kumar |
| Grid Simulation Release 3 | Grid Integration | 05 Nov 2026 | 05 Nov 2026 | 0 days | On Track | Validated | Prof. S. Venkatesh |
AI InferenceVariance interpretation
Two milestones carry forecast variance. Both trace to blocking dependencies rather than research progress: procurement on Clean Energy and a missing validation report on Bioengineering.