Finance

Funding & Resource Visibility

Sanction, utilisation and commitment status maintained continuously from approved systems.

Sanctioned

₹120 Cr

Received

₹95 Cr

Utilised

₹78 Cr

Committed

₹11 Cr

Available

₹17 Cr

Utilisation

Energy Storage₹26 Cr of ₹38 Cr · 68%
Materials₹22 Cr of ₹32 Cr · 69%
Systems₹17 Cr of ₹26 Cr · 65%
Bioengineering₹7 Cr of ₹14 Cr · 50%
Human Capital₹6 Cr of ₹10 Cr · 60%

Project Utilisation

ProjectSanctionedUtilisedUtilisation %VarianceOpen ProcurementRisk
Clean Energy Storage Pilot₹12 Cr₹7.8 Cr65%On Plan₹1.4 CrAt Risk
Advanced Materials for Storage₹16 Cr₹11.2 Cr70%On Plan₹0.6 CrHealthy
Bio-derived Energy Materials₹9 Cr₹4.1 Cr46%Under-utilised₹0.3 CrMedium
Grid Integration & Systems₹14 Cr₹9.4 Cr67%On Plan₹0.9 CrHealthy
Capacity Building & Skilling₹6 Cr₹3.9 Cr65%On Plan₹0.1 CrHealthy

Procurement → Milestone Risk

Battery order

₹85L

PO pending

Linked milestone
Industry Field Trial
Due
30 Sep 2026
Potential impact
+8 days
View dependency

Data sourced from approved finance / procurement systems. Morelo does not replace the institutional ERP or write back to it.