Overview

Grid Integration & Systems

Model and demonstrate high-penetration storage integration for state grid operators.

PI

Prof. S. Venkatesh

Budget

₹14 Cr

Utilisation

₹9.4 Cr

Period

Apr 2024 – Mar 2029

Partners

5

Theme

Systems

Project Summary

Objective
Model and demonstrate high-penetration storage integration for state grid operators.
Current status
Simulation milestones met; utility data-sharing agreement signed.
What changed Source Fact
  • Battery procurement delayed by 18 days
  • Partner site readiness pushed from 15 Sep to 24 Sep
  • Field trial remains due 30 Sep
  • Validation protocol has been approved
  • Prototype v2 testing completed
AI InferenceAI interpretation
The technical workstream remains healthy, but the current dependency chain materially increases delivery risk for the September field-trial milestone.
View sources

Milestone Health

  • Prototype v2.0

    Evidence validated

    Completed
  • Industry Field Trial

    Procurement + partner site

    At Risk
  • Final Validation

    Depends on field trial

    Upcoming
  • Technology Transfer Assessment

    Q1 2027

    Planned

Next Management Action

Escalate battery procurement and confirm revised delivery date by 9 Sep.

Why

The field trial has only a 6-day buffer after revised partner-site readiness.

Suggested owner

PMO + Procurement Lead