Overview

Bio-derived Energy Materials

Establish bio-derived material pathways for low-carbon storage components.

PI

Dr. Karan Shah

Budget

₹9 Cr

Utilisation

₹4.1 Cr

Period

Oct 2024 – Sep 2028

Partners

2

Theme

Bioengineering

Project Summary

Objective
Establish bio-derived material pathways for low-carbon storage components.
Current status
IP filing has slipped pending a validation report; spend is materially under plan.
What changed Source Fact
  • Battery procurement delayed by 18 days
  • Partner site readiness pushed from 15 Sep to 24 Sep
  • Field trial remains due 30 Sep
  • Validation protocol has been approved
  • Prototype v2 testing completed
AI InferenceAI interpretation
The technical workstream remains healthy, but the current dependency chain materially increases delivery risk for the September field-trial milestone.
View sources

Milestone Health

  • Prototype v2.0

    Evidence validated

    Completed
  • Industry Field Trial

    Procurement + partner site

    At Risk
  • Final Validation

    Depends on field trial

    Upcoming
  • Technology Transfer Assessment

    Q1 2027

    Planned

Next Management Action

Escalate battery procurement and confirm revised delivery date by 9 Sep.

Why

The field trial has only a 6-day buffer after revised partner-site readiness.

Suggested owner

PMO + Procurement Lead