Bio-derived Energy Materials
Establish bio-derived material pathways for low-carbon storage components.
DelayedView in graph
PI
Dr. Karan Shah
Budget
₹9 Cr
Utilisation
₹4.1 Cr
Period
Oct 2024 – Sep 2028
Partners
2
Theme
Bioengineering
Project Summary
- Objective
- Establish bio-derived material pathways for low-carbon storage components.
- Current status
- IP filing has slipped pending a validation report; spend is materially under plan.
- What changed Source Fact
- Battery procurement delayed by 18 days
- Partner site readiness pushed from 15 Sep to 24 Sep
- Field trial remains due 30 Sep
- Validation protocol has been approved
- Prototype v2 testing completed
AI InferenceAI interpretation
The technical workstream remains healthy, but the current dependency chain materially increases delivery risk for the September field-trial milestone.
Milestone Health
- Completed
Prototype v2.0
Evidence validated
- At Risk
Industry Field Trial
Procurement + partner site
- Upcoming
Final Validation
Depends on field trial
- Planned
Technology Transfer Assessment
Q1 2027
Next Management Action
Escalate battery procurement and confirm revised delivery date by 9 Sep.
Why
The field trial has only a 6-day buffer after revised partner-site readiness.
Suggested owner
PMO + Procurement Lead