Capacity Building & Skilling
Train researchers and industry engineers on storage systems and safety.
On TrackView in graph
PI
Dr. Nandini Iyer
Budget
₹6 Cr
Utilisation
₹3.9 Cr
Period
Apr 2024 – Mar 2029
Partners
4
Theme
Human Capital
Project Summary
- Objective
- Train researchers and industry engineers on storage systems and safety.
- Current status
- Cohort 3 completed; industry placement reporting in progress.
- What changed Source Fact
- Battery procurement delayed by 18 days
- Partner site readiness pushed from 15 Sep to 24 Sep
- Field trial remains due 30 Sep
- Validation protocol has been approved
- Prototype v2 testing completed
AI InferenceAI interpretation
The technical workstream remains healthy, but the current dependency chain materially increases delivery risk for the September field-trial milestone.
Milestone Health
- Completed
Prototype v2.0
Evidence validated
- At Risk
Industry Field Trial
Procurement + partner site
- Upcoming
Final Validation
Depends on field trial
- Planned
Technology Transfer Assessment
Q1 2027
Next Management Action
Escalate battery procurement and confirm revised delivery date by 9 Sep.
Why
The field trial has only a 6-day buffer after revised partner-site readiness.
Suggested owner
PMO + Procurement Lead