Clean Energy Storage Pilot
Develop and validate scalable energy-storage technologies for grid and industrial applications.
At RiskView in graph
PI
Prof. Anil Kumar
Budget
₹12 Cr
Utilisation
₹7.8 Cr
Period
Apr 2025 – Mar 2028
Partners
3
Theme
Energy Storage
Project Summary
- Objective
- Develop and validate scalable energy-storage technologies for grid and industrial applications.
- Current status
- Research development is broadly on plan, but field validation is exposed to a procurement delay and partner-site dependency.
- What changed Source Fact
- Battery procurement delayed by 18 days
- Partner site readiness pushed from 15 Sep to 24 Sep
- Field trial remains due 30 Sep
- Validation protocol has been approved
- Prototype v2 testing completed
AI InferenceAI interpretation
The technical workstream remains healthy, but the current dependency chain materially increases delivery risk for the September field-trial milestone.
Milestone Health
- Completed
Prototype v2.0
Evidence validated
- At Risk
Industry Field Trial
Procurement + partner site
- Upcoming
Final Validation
Depends on field trial
- Planned
Technology Transfer Assessment
Q1 2027
Next Management Action
Escalate battery procurement and confirm revised delivery date by 9 Sep.
Why
The field trial has only a 6-day buffer after revised partner-site readiness.
Suggested owner
PMO + Procurement Lead